WJON — The demolition of Holes Hall at St. Cloud State University will be getting under way in earnest this week.
Dan Pederson is the director of Residential Life. He says they’ve been doing a lot of interior demo work over the past couple of weeks. We’ve removed all the hazardous materials through the abatement process. We’re beginning the shutdown of utilities. The elevator has been removed. And now we’re essentially gutting the interior of recyclable materials.
Pederson says the heavy equipment will be arriving on campus this week. Most of the deconstruction will be done by the time the students return on August 18th, but there will be some finishing work that will last into November.